Hi,
I tried to change the vendor code in a Scheduling Agreement using MEMASSSA, but the change was not effected. do you know if it is possible to change this field in an SA using MEMASS? if not, is there any other way to do it other than creating a new SA?
Thank you very much.
i do not think so that the vendor code can be changed since the SA is going to be created for vendor correct and if a agrrement is created for a vendor , how can be the vendor changed?
The thing is that the SA was created with the incorrect vendor code, so, instead of creating a new SA, it would be helpful if there were any way to just change the vendor code in that SA.
Hi,
Better check for the SA deletion and create the new ones...
Even i don't think that it'll be possible bcoz the VENDOR code is the most important code based on which long term agreement is done...
Regards
Priyanka.P