Hi,

 

In work center I have maintained u201CStd. queue timeu201D and it got copied to Routing also. Now when I am creating production order, this que time is not being considered. I mean it is not getting copied to production order and scheduling is not happed accordingly. Can anybody suggest me where I am doing mistake?

 

Regards,

  • Re: Que time is not being considered in Lead time scheduling
    karthick PP
    Currently Being Moderated

    For the control key corresponding to the work center,please check whether you have ticked the indicator for scheduling..

     

    in work center, pls check the what s the control key..

     

    For the control key,in OP00 check whether he scheduling indicator is checked..

     

    If you have nt maintained any control key in the work center,then check the operation that uses this work center(in routing). Here you should have specified a control key. Pls check similarly for this cotrol key.

     

    Generally preference will be given for routing than the work center.

     

    Karthick P

     

    Edited by: karthick PP on Sep 29, 2010 10:15 AM

     

    Edited by: karthick PP on Sep 29, 2010 10:16 AM

  • Re: Que time is not being considered in Lead time scheduling
    Jiaul Haque
    Currently Being Moderated

    Dear

     

    Check the following :

     

    1.Check in OPU3 -Define Production Scheduling Profile -you include this reduction type in All Operation , Max reduction level ,% in reduction in Float .

     

    2.Check wether any reduction strategy assinged with Que Time percentage for your plant in OPJS  .This basically the percentage of reduction in various operation timing like Move Time ,Que Time , Inter-operation Time to optimise the Scheduling .This reduction can be by Overlapping and Spliting based on the setting in OPJS.

     

    3.Check in OPU3/OPU5 -Scheduling parametrs wether , you have maintained reduction type  , percentage of reducetion in floats   , reduction level ,

     

    revert and come back

    Regards

    JH

    • Re: Que time is not being considered in Lead time scheduling
      Chetan Chetan
      Currently Being Moderated

      Hi Jiaul Haque ,

       

      Thanks for your detail reply,

       

      I have chacked pointwise given by your but

       

      In OPU3 (Specify scheduling parameters) I have maintained,

       

         Reduction type-All operations in the order will be reduced

         Max reduction level u2013 Do not reduce

         % reduction u2013 all zeros

       

      In OPJS, reduction strategy u201C01u201D is assigned for my plant.

       

      So, any impect because of this?

       

      Regards,

      • Re: Que time is not being considered in Lead time scheduling
        Jiaul Haque
        Currently Being Moderated

        Dear

         

        OPU3  you should maintain :

         

        Reduction type-All operations in the order will be reduced-Correct -means where ever you have Ques time in operation or with the operation , you are asking system to reduce  basef on scehduling parametres .

         

        Max reduction level u2013 Do not reduce -Wrong -it should be Do not reduce beyond the reduction level 1 -means  as per reduction

         

         

        stategy 01( OPJS) , 50% of que time will be cosidered for reduction .

        % reduction u2013 all zeros -Wrong- it shoud be based on the operation level -how much percentage you want to reduce the Flaot times based on scheduling margine key cos FBP/FAP are contributing to Scheduled Star and Schedule finsih date .

         

         

        Hope its clear

        regards

        JH

        • Re: Que time is not being considered in Lead time scheduling
          Chetan Chetan
          Currently Being Moderated

          Hi Jiaul Haque ,

           

          I appreciate your reply.

           

          In my case I want to consider Que time while scheduling and operation dates also need to be updated in production order. This is my reuqirement.

          So, can tell me what to maintain in OPU3 and OPJS to get this?

           

          Regards,

          • Re: Que time is not being considered in Lead time scheduling
            Jiaul Haque
            Currently Being Moderated

            Dear ,

             

            In OPU3/OPU5 -Define schedulnig parametrs you should keep the following parametrs to get the Production Schedule Start and Finsh Date :

             

            1.Mark Scheduling and Generate Capacity Requirement  check box

             

            2.Adjust Scheduling : Adjust Basic Date , Adjust depedent Requirement to operation date

             

            3.Scheduling Type : Bacward

            4.Start date in the past : If you want to start the scheduling of Production Order in older date , then you can maintain how many day  system can schedule forward .It means if you keep 30 days , then Planned order or Production Order , which has older start date , then system will do Forward schedule even it is set to backward .

             

            5.Requirement Date determination for compiepent : Setup

             

            6.Reduction : As per the eralier posting .

             

            OPJS: Standard set up  as available for 01

             

            Hope this helps