Confirmation Transfer Issue through CATA run

Former Member
0 Kudos

Hi All,

In CJI3 report, still Actual Cost is appearing against reversed timesheet entry.

Scenario: User had done some timesheet entry against Network activity and ther CATA job run. After some days, User again changed the timesheet with New Network and Activity number. But still CJI3 report is showing cost against old Netowrk Number. Its not getting Cancelled/reversed. In CAT2/CADO/CATS_DA its appearing properly.

I think there may be some issue in CATA job run.

Could you please tell me what are the possible causes that s why these confirmation can not get cancelled?

Also if you provide solution, then it would be great for me.

Many Thanks in advance.

Swapnil Kharul

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Not got any specific reply so closed this thread.

Former Member
0 Kudos

Hi All,

Any guess...?

Swapnil Kharul

Former Member
0 Kudos

Hi All,

Can anybody suggest regarding above mentioned issue?

Swapnil Kharul

Former Member
0 Kudos

Check with PS consultant wheather activity type/WBS element is closed or open .old activity type/WBS may be closed. we cant make the entry changes,thts why in report its showing the old one

Former Member
0 Kudos

Hi,

Thanks for your reply.

I have checked NWA is not closed and WBSE also not Closed when CATA run.

Please sugeest.

Swapnil Kharul