Hi All,
In CJI3 report, still Actual Cost is appearing against reversed timesheet entry.
Scenario: User had done some timesheet entry against Network activity and ther CATA job run. After some days, User again changed the timesheet with New Network and Activity number. But still CJI3 report is showing cost against old Netowrk Number. Its not getting Cancelled/reversed. In CAT2/CADO/CATS_DA its appearing properly.
I think there may be some issue in CATA job run.
Could you please tell me what are the possible causes that s why these confirmation can not get cancelled?
Also if you provide solution, then it would be great for me.
Many Thanks in advance.
Swapnil Kharul
Not got any specific reply so closed this thread.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi All,
Any guess...?
Swapnil Kharul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.