on 11-01-2010 4:54 PM
Hello Gurus,
In case a project (or WBS element) was excluded during Overhead calculation (CJ45) in the prior month and the prior month is already closed, is there a way to retroactively calculate the overhead in the prior month and post it in the current month?
Thanks in advance.
Arnold
you can run the overhead for the previous month and then for this month - should post costs for the current month - try and check out
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.