Plant assignment to more than one sales org

Former Member
0 Kudos

We have a business process where certain products made in one plant have to be sold to two sales organizations depending on certain conditions defined in the sales view of the material master. How can this be achieved? Currently system does not allow for plant assignment to more than one sales org?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Have you checked in OVX6 ? You can assign a given plant to different Sales Org. - Distribution Channel.

Select the Sales Org. - Distbn. Channel, click on Assign & in the pop-up box select the plant.

Regards,

Vivek

Former Member
0 Kudos

Vivek,

Thanks for your answer it was helpful. One follow-up question....when a STO is created from a plant, is there a way to let the system pick up (via an user exit or something) the correct sales org depending on master data information given in the sales view for the material?

Former Member
0 Kudos

Hi,

STO with Sales Org?? Can you explain what business process you're performing and how you intend to map it in system. Also what information you've maintained in the material master sales view.

A little more details would help for a better understanding.

Regards,

Vivek

Former Member
0 Kudos

Kicks,

This is normally part of STO config. IMG > MM > Purchase Order > Set up Stock Transport order > Define shipping data for plants.

Best Regards,

DB49

Edited by: Dogboy49 on Nov 4, 2010 5:17 PM