on 11-04-2010 7:18 AM
Sir,
At the time of confirming production order in CO11N message " Production order is closed " appears although production order status is released, partly confirmed, already coasted.
Thanks
Dear Vijay,
As per Std SAP you cannot confirm the order, if the order status is closed
So Just revoke the closed status
Then perform the final confirmation
Regards
Madhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check your production order status if it contains CLSD.
Is your production order ediatble in co02.
check you are entering corrrect production order number in co11n.
If the order has closed status then remove the closed status as suggested by other forum experts.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.