I need one clarification, in the rough cut planning, the existing load
is not considering for available capacity.It is considering only from
the resource capacity.
E.g : Avaialble capacity of for Resource A (today) is 24 hr
One Order is created and released for 4 hr with Resource A
As per that now my available capacity of the resource is only 20 hr
In SOP planning view, it showing as 24 hrs.
And If i am running the SOP today at 1400hrs for calculating the
resource capacity. Practically my avaialble capacity is 10hrs. But
in the system it showing as 24hrs.
How to capture the above both requirements?
2. Through roughcut planning we can able calcualte the cost, material and
PRT availability also. But it is not coming the the SOP screen.
Is it any configuration i missed out? Help me out
Regards,
sakthivel
<Title of the thread has been changed. Please use meaningful title.>
Edited by: Csaba Szommer on Nov 15, 2010 9:52 PM
Edited by: Csaba Szommer on Nov 15, 2010 9:58 PM
Hi!
Available capacity means the total capacity available for use in production. Presence of an requirement will not reduce the available capacity.
Regarding SOP. Check for the starting time of the order or requirement. See if you can schedule from the current time instead of start of the day.
Regards,
S.Satish Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.