cancel
Showing results for 
Search instead for 
Did you mean: 

Splitting in Process Orders

Former Member
0 Kudos

Hello,

We are currently trying to Split the Process Orders like we do the Production Orders. We have maintained the required settings but still cann't find the option to Split it in the Process Order. Can you please help?

Accepted Solutions (1)

Accepted Solutions (1)

sundaresan_velayudam
Active Contributor
0 Kudos

Order Splitting is not possible in PP-PI and REM,

Former Member
0 Kudos

Is there any custom exit/BADI?anything through which split in process order can be enabled

sundaresan_velayudam
Active Contributor
0 Kudos

I am Not aware of the BADI / customer exit for order splitting. in process order, We will wait for our Expert reply for this

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please have a look into this link. It may be help you some more.

http://help.sap.com/saphelp_di46c2/helpdata/en/8e/fec838f5fb9763e10000000a114084/content.htm

Naren

Former Member
0 Kudos

Hi naren,

Thanks for the link. It might work for us, Only if we know the process to Split the Order. The link does tell the functionality but does not specify the steps. Can you please proivde that.

Regards,

Yogesh

Edited by: Yogesh Pegoria on Dec 10, 2010 12:56 PM