on 12-10-2010 12:34 PM
Hi,
When we create a process order , system assigns the confirmation no for each of the operation & these confirmation numbers are in sequence.
In our case we have activity numbers in the recipe as 0010, 0020, 0030, 0040, 0050, 0060...... Subsequently we have inserted operations..now the sequence has become 0010, 0020, 0030, 0040, 0041, 0042, 0050, 0060...... Now when we create the process order, the confirmation numbers for operations 0041, 0042 comes after 0060. We have a development which has a pre-requisite that the sequence of confirmation no's should be as per sequence of operations.
Any idea how to achieve the correct sequence of confirmation no's?
regards,
Mohit
Mohit,
My simple sugestion would be delete the operations/phases 0050 and 0060 and latter on add the new ones and next the operations of 0050 & 0060.
Or
Correct your developed object to pick up confirmation number based on operation number referance.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Mohit,
I have find the route cause BUT I Don't know how to fix it
Based on Operation ID, system is creating a confirmation No
Since you have created a operation 41 and 42, System gives the operation ID next to 60
Thats the reason system is giving the confirmation No after 60
I don't know how To add operation ID in routing
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.