3 Replies Latest reply: Jan 17, 2011 4:11 PM by Jiaul Haque RSS

Fixed Cost & Variable cost in Production Order

kumar k
Currently Being Moderated

Hi  ,

       I have maintained the fixed cost & Variable cost in  KP 26 for the activity type .

 

for 1 hr

Fixed cost : 1

Variable cost :1

 

Operation duration is 1 hr , when i check the Planned cost it shows total plan cost is 6.92 ,

Fixed cost as 3.46 and variable cost as 3.46 ,

 

How the system calculates 6.82 ,

 

I have maintained the valuation Variant for the activity type is Plan price for the period .

 

As per my understanding system has to calculate the Planned cost as 2 (1 for fixed + 1 for Variable )

 

Can anybody explain me why the system calculated the price as 6.82 ...

 

Thanks in Advance ...

Actions