Sending mails to some mail IDs on Thursday & Monday using process chain

Former Member
0 Kudos

Hi Experts,

I have a process chain that runs daily.

My requirement is to send mails to some IDs on Thursday & Monday when my process chain is finished.

I know we use create message option on the last process of my chain to send mails , but i want to send mails only on those specific days. I want your help to make this happen. Please let me know how this can be done.

Thanks,

Sandeep.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

use RSPC-> General Services-> Decision Between Multiple Alternatives

You can create two alternaitves(options) via a Formula, one for MON&THU and one for the rest.

Greetings