2 Replies Latest reply: Feb 21, 2011 9:23 AM by Jiaul Haque RSS

mass strategy group change - 40 to 52

raphael labourasse
Currently Being Moderated

Hi experts,

 

I want to change strategy group from 40 to 52 for about 2000 materials.

 

It implies that PIR type and customer reqmt type change from VSF/KSV to VSE/KSVS.

 

Mass PIR change is not a problem because PIR are transfered from an APO system.

 

But then there is an issue with existing schedule lines with customer reqmt type KSV which don't

consume anymore the PIR.

 

Is there a standard tcode or program to mass update the schedule lines rqmt type ?

 

What is the good practice to perform this change ?

 

Thanks in advance,

 

Raphael

  • Re: mass strategy group change - 40 to 52
    Sundaresan Velayudam
    Currently Being Moderated

    Use MM17

     

    select the table MARC- field STRGR for strategy group 

     

    and execute

     

    enter the 2000 Material code in multiple selection option and plant

     

    enter the 52 in new value and click carry out mass change and save

     

    test in dev server and then carryout in PRD server

     

    this will solve your problem

  • Re: mass strategy group change - 40 to 52
    Jiaul Haque
    Currently Being Moderated

    Dear

     

    If u Have the Idea of LSMW then try to do the changes wht ever u want by LSMW ...

     

    It will be much easy for mass Changes .Otherwise , you need to first delete all the the PIR's of VSF requirement type using transaction MD62 , once PIR is delete you need to run MRP in "Delete Recreate Mode". Planned orders which are firmed will not be automatically deleted in MRP run , you cal delete these orders in MASS using transaction MD16.

     

    Next would be to check all the sales order which derived VSF/KSV  procurement requirement type, you need to delete this line item and need to create new ones with VSE/KSVS.  requirement type.

     

    To carry on material level changes for planning startegy , either u should goto MASS/MM17 but it will not affect the exixting deamand or Customer Requireimenet .You need to changes the Requirement Type at PIR-SChedule line as well as Customer requirement Type .

     

    Regards

    JH

     

    Edited by: Jiaul Haque on Feb 21, 2011 9:21 AM

     

    Edited by: Jiaul Haque on Feb 21, 2011 9:22 AM