Dear friends,
I have given seven day packages for all the operations in the maintenance task lists and assigned the same strategy in the maintenance plan. The problem is I am getting the maintenance call object 7 days before the plan date.I.e the plan date for the order is on 23/02/2010 but the maintenance order is released on 16/02/2010 itself. The call horizon is 90% and scheduling period is 999 days and cycle is 7 days
Cycle modification is 1.00 and all the remaining are blank( no buffer is used).
With regards,
V.Vijay Kumar
You released it in back date on 16/02/2011, that is why it give date 23/02/2011
It calculate 16/02/2011 + 7 = Due date is 23/02/2011