cancel
Showing results for 
Search instead for 
Did you mean: 

Month end closing: Fixed Price in KSII differ to KP27

Former Member
0 Kudos

Hi,

Kindly help, when my user executes KSII for month end closing, the Fixed Price OC in KSII is differ with KP27.

Please advice.

Thanks.

Mari

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

hi..

Price is calculated in Vari & fixed as per your plan in KP06. However you follow the steps to get vari & fixed price:

.KP06 1-101 Cost Centre Planning - element planning (Fixed value & Variable Value

1-102 Activity Distribution to findout Fixed/Variable Price

if both are required paln Variable quanty

otherwise Fixed qty

KP26 1-201 Activity Planning (Activity qty)

Pl revert back if your issue is resolved.

kkumar

Former Member
0 Kudos

hi..

T.code KSBT

kkumar

Former Member
0 Kudos

Hi,

When i went to Tcode: KSBT to check, there are some cost fall under Fixed Price in OC and some fall under Varible Price in OC,depend on the Activity Type. Ex. Electricity is under Var Price OC, and Operation Cost is under Fixed Price OC.

However, in KSII, all of the price is allocated in Fixed Price OC only.

Can you please advice what shoud i do to get the correct price in KSII.

Thanks.

Mari

Former Member
0 Kudos

hi..

Your question is something confusing.

KSII is for actual price and KP27 is for plan price.

You goto KSBT and see the price for Actual select price indicator 5 and for plan 1 or both at a time.

kkumar

Former Member
0 Kudos

Hi,

In that case, please advice which Tcode i should use to see the actual price.

Thanks.