Hi i am having two reports, first report runs for 10 minutes , i want the second report to run automatically after first report is completed. how to do that?
Create a schedule event in the CMC.
Click Schedule on the report that needs to be triggered by the first report. Set recurrence and other options.
Add the event to the "Events to wait for" list in the Events section.
Schedule the first report to run, choose a recurrence and set needed options, and add the event to the "Events to trigger on completion" list in the events section.
Admin guide also has a section on creating schedule events
http://help.sap.com/businessobject/product_guides/boexir31/en/xi3-1_bip_admin_en.pdf
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
i did the way u told but the second report is not running once the first report is success or failure.
fro report1 I added the event to the "Events to trigger on completion" list. and added the event to the "Events to wait for" fro my second report.
my recurrence for the second report is "now".
the event needs to be triggered within the start and end time (try scheduling "once" with a specific time interval).
From the admin guide:
Scheduling objects based on an event
When you schedule an object that waits for a specified event, the object will
run only when the event is triggered, and only when the rest of the schedule
conditions are met. If the event is triggered before the start date of the object,
the object will not run. If you have specified an end date for this object, and
if the event is not triggered before the end date occurs, the object will not
run because not all of the conditions will have been met. Also, if you choose
a weekly, monthly, or calendar schedule, the object will have a specified time
frame in which it can be processed. The event must be triggered within this
specified time for the object to run. For example, if you schedule a weekly
report object that runs every Tuesday, the event must be triggered before
the end date of the instance (the end of Monday, in this example).