Dear All ,

How to set Release strategy in PO , after release the PO Price will be update in PO table with out release the PO no Price will be update .

when user create PO everything will seen if he check in me22n he can get the price . but not update in table .

how to do it

Regards

Shiv

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Release strategy is just an electronic approval process., through which authorised persons can approve ur document.

according to my knowledge, PO Price is not concerned with release strategy .

but yes, if u want u can use the the conditions like Release expected materialm price.

i think u know how to create RS.

first create characteristics, then class then set complete RS (R- group, R-code, R-indicator, then finally release strategy).

thanks

Edited by: Ms. nisha on Mar 16, 2011 11:50 AM

Answers (2)

Answers (2)

former_member1296478
Participant
0 Kudos

closed

Former Member
0 Kudos

The question is fundamentally incorrect. If such things required look at PR.

Once you do P.O , price will update in the standard table. If you want total Z- , feasibility can be discussed with ABAPER,

Genreally Release is concerned with certain criteria , price may be one criteria, but without Price standard P.O can't be created , hence ME22N , comes latter.