0 Replies Latest reply: Mar 22, 2011 6:59 AM by nasir ilyas RSS

Copy Verson

nasir ilyas
Currently Being Moderated

Dear all

 

I have a scenario, after running the MRP if there is change in Forecast for some products of one plant, i make inactive version for the new requirements and copy it to active version ( mc78), while copying, it completely overwrite the active version for all plants n just show the newly copied version requirement in MC76, what i need is , it just make changes in those materials for which changes have been made, plz guide me how to do this.... as i need to maintain records for all changes

 

regards

Actions