batch to batch transfer (same material)

Former Member
0 Kudos

HI experts,

I have a scenario where i have to post the X qty from batch B ( GRN in april ) to batch A (Grn In mar) for same material.

I have consumed the material from full qty from Batch A in April and the material from batch B remained unutilized.

Now i have to consumed some more material in the month of March . Period is still open.

What is the solution as i tried batch to batch transfer using 309 but error appears "Deficit of BA :Unresticted material".

What is the alternate solution for this?

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

if batch B was created in April, then you cannot move its stock in March, as you did not have any stock of this batch in March.

Because of this fact, you cannot perform a transfer posting in one step.

You have to use a 2 step movement, e.g. 201 to consume the batch B to cost center in April, and a 202 to unconsume this quantity with batch A in MArch.

Former Member
0 Kudos

Thanx. How to do inconsumpption i.e. 202 (using which Tcode)

JL23
Active Contributor
0 Kudos

MIGO or MB1A, just the same as you do the goods issue to cost center with 201, just exchanging the movement type and using a different posting date

Former Member
0 Kudos

Thanks > Jurgen.