hi gurus
what is the difference between required date and base date in reservation , mb21 , mb24
regards
leo
Hello LEO,
Base date for reservation
Specifies the date for which the goods movement is planned.
Use
For each item of the reservation, the system uses this date as the default value in the Requirements date field. However, you can change the requirements date in the individual items.
Thanks & regards,
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Base date:Specifies the date for which the goods movement is planned
Requirement date:Specifies the date on which the requested quantity of material is required.
In the case of a reservation, the date on which it is planned to issue or receive the material.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.