7 Replies Latest reply: Jul 19, 2011 8:53 AM by Vengaiah Chowdary Pachava Chinna RSS

Project Progress Catch-up Plan

Aparna Chaganti
Currently Being Moderated

Dear PS Friends,

 

I would like to know if any of you have worked on Project Progress Catch-up Plan.

 

Basically, it is the third dashed-curve which comes in a project progress graph of plan vs actual to cover u2013up the delay.

 

Below is an example to explain this.

 

M3 being the current month.

 

Months     M1     M2     *M3*     M4     M5     M6     M7     M8     M9
Plan PoC     0%     12%     20%     35%     42%     52%     60%     72%     90%
Actual PoC     2%     7%     12%                              
Catch-up               12%     18%     24%     40%     52%     72%

      

      

 

If yes, please let me know and also how we can implement in SAP PS.

 

Thanks in advance for your help!

 

Regards,

Aparna