production order Target cost

Former Member
0 Kudos

Hi,

I need a solution for Production order Target cost Updation In AFS. How the target cost will be updated in the Production order?

I tryed in all methods and gone though with SPRO settings but the result is nill. So, please let help me out if any one working with AFS SAP PP.

Thanks & Regards,

Madhu.G

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I have not worked on AFS, but believe the process should be same as non-AFS.

Once the order is completed, ask your FI people to run variance as a part of the settlement process, then check the Target cost. I would strongly suggest that you work with your FI/Co person for this. It is quite a straight forward method.