Error in Conversion of Planned order to Production order

uday kiran
Currently Being Moderated



When I am converting planned order to production order I am getting error


"Planned order 234144 is not to be converted

Message no. CO041



You tried to convert a planned order in which the conversion indicator has not been set.


System Response

The system does not convert the planned order.



Set the conversion indicator (detail screen, make-to-stock production) in the planned order 234144."


So I went to MD12 and activated the conversion indicator. And when I try to convert to PO in CO40 I am getting the below error


You cannot make an assignment to make-to-order stock

Message no. CO684



The component cannot be allocated to an individual stock because make-to-order production and engineer-to-order production cannot be executed with this order.


A possible cause is that you are trying to create an order with reference to a sales-order/project, where an account assignment to a sales order/project is not allowed in the settlement profile that is assigned to the chosen order type. This is inconsistant.


System Response

The following responses are possible:


Order processing is cancelled.

The system resets the special stock indicator back to the original value.


Choose another order type.



So is it like every time I have to go to MD12 for every planned order to be converted to PO and activate the conversion indicator.??


Please teach me the reasond above the two errors.