CK40N Future standard cost estimate is locked

M Tse
Currently Being Moderated

Dear All,

 

We are doing ck40n and try to release the cost estimate. But error CK711 Future standard cost estimate is locked for this company code B.

 

We have another company code A already completed cost estimate. But we found some materials cannot be release and Future Cost in Materail master. Also said no authorization on company C, and D which is totally not related.

 

Can anyone give me some hints ?

 

Thanks a lot