on 08-24-2011 6:19 AM
Hi friends
We are using the phasing in/phasing out of a couple of products and have issue explianed as follows:
Product A001 27057860 will phase out on 07.10.2011 and after a some period on a different Product code, it will phase come in again from 09.12.2011. However, APO does not allow us to do this, because the phasing out date is before the phasing in date.
Any idea/thought this can be modelled in APO dp in some other way?
Rgds,
SB
Hi SB,
Do you want to phase-in the same material, which is phased-out earlier?
If so, change the validity time of your phase-out and phase-in profile assignment. please make sure, they are not overlapping.
I think by this, we can avoid the phase-in and phase-out are not getting validated during forecasting on the same period.
Regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.