PO commitment - Not able to close the project

former_member214272
Contributor
0 Kudos

Hi

When we tried to close the Project , it shows the message PO commitment for WBS.

We checked the PO it was completed and marked for Deliv .Completed and Final invoice is also done.

We check the CJI5 and table COOI it shows the commitment against PO.

RKACOR04 and RKANBU01 we executed the mention program also to correct the commitment but didn't help.

Can you please provide some input to fix the issue.

from which table COOI values are update ?

Thanks

Sunil Jawalkar

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Could you please implement the following OSS notes:

1491430 - Incorrect Commitments for Service Items

1492317 - Incorrect commitments after posting service entry sheet

And then perform the following steps after the notes have been applied:

1) We need to execute the RKANBU01 transaction to re-build the commitments. I actually executed it and the commitments were re-built properly.

2) Now you in order to correct the FM records we will have to execute FMN4N transaction for the affected PO, I indeed executed that also.

Hope this resolves your issue.

Regards,

Syed Ammar Zaheer

0 Kudos

Hi,

Use 'Recalculate the price' option in the PO change mode (Services full screen mode: Service specification --> Price --> Recalculate) and save the PO. Please check the commitment report.

Former Member
0 Kudos

Edit the PO and save again to recalculate the Prices. This may also work sometime

Former Member
0 Kudos

Hi,

Did you run CJEN after those correction programs. If not pleasetry that as well.

Regards

Sreekanth

Brendan_Ward
Advisor
Advisor
0 Kudos

Hi Sunil,

Are you using services on the PO? If so, then review SAP Note 735404.

Best Regards,

Brendan