HI,

Can you give me some help on setting up a rework process for process manufacture factory?I don't see some function in PI factory, like reference operation set (trigger point)in discret manufacture factory....I don't know how to make it...thanks..

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

Open routing and select the operation line item

To assign the Trigger Point function press GOTO MENU and then select Trigger Point Overview

enter trigger point usage and description

Now select trigger point usage line item and click DETAILS menu and select "TRIGGER POINT"

Create Routing Trigger Point Details will appear

Select the check Box="Insert reference operation set"; Sys Status=PCNF; Active=1

now on the top Press the "PARAMETERS BUTTON" assign the group and group counter

come back to the operation overview and save

Regards,

Raj

Former Member
0 Kudos
former_member311826
Active Contributor
0 Kudos

Dear Yang,

There are so Many threads available on Rework. Please go through it.

Also go through the blog for the same.

vasudevap_pushpalas
Active Contributor
0 Kudos

Dear

Rework order process:

Create order through CORO.

Using CORO t-Code create production order with Order type=RW01.

In that select reference operation set enter group number and task list type=S

Mention the Main order Process ordernumber in the settlement profile of rework order.

Issue good if you want to isue any components

Confirm rework order

TECO the rework order

Now do GR of main process order.

With Regards

Pushpalas

Edited by: pushpalas on Oct 17, 2011 3:01 PM

former_member183783
Contributor
0 Kudos

HI,pushpalas and all of you:

thanks very much for your quick reply..

but I need a rework process for PI...I can't find a trigger point function in C201(reciept) to insert a reference operation set...can you tell me how to make it via process order(reciept,resource) instead of production order(router,work center)..

thanks..

sundaresan_velayudam
Active Contributor
0 Kudos

Dear Monst Yang,

To my knowledge Trigger point is not possible in PP PI as well as in REM ( trigger point is only possible in Discrete Industry), if you want to create a rework order with out material, then you need to create manually in CORO

Regards,

Sundaresan.E.V

Former Member
0 Kudos

HI,pushpalas and all of you:

> thanks very much for your quick reply..

>

> but I need a rework process for PI...I can't find a trigger point function in C201(reciept) to insert a reference operation set...can you tell me how to make it via process order(reciept,resource) instead of production order(router,work center)..

>

>

> thanks..

Hi,

The below mentioned process hold good for Discrete as well as Process manufacturing

Let it be normal routing or master recipe

Open routing and select the operation line item

To assign the Trigger Point function press GOTO MENU and then select Trigger Point Overview

enter trigger point usage and description

Now select trigger point usage line item and click DETAILS menu and select "TRIGGER POINT"

Create Routing Trigger Point Details will appear

Select the check Box="Insert reference operation set"; Sys Status=PCNF; Active=1

now on the top Press the "PARAMETERS BUTTON" assign the group and group counter

come back to the operation overview and save

Regards,

Raj

former_member183783
Contributor
0 Kudos

Hi,

I use COR2 and go to the operation view..But I don't see the "trigger point overview" or "trigger point"..Did you test it in process manufacture?or I need to do some config?thanks..