Dear CONS
WHEN WE TRANSFER MATERIAL TO VENDOR (SUBCONTRACT)UNDER 4(5)A CHALLAN , THIS VENDOR IS NOT SEEN IN T-CODE- MBLB. WHAT IS THE SOLUTION.
Dear,
MBLB shows vendor - check layout.
Secondly if you click on material document icon available on (CtrlShiftF7) here you will get material document with document date. If vendor not shown here, click current display variant (Ctrl+F8) to get vendor.
Regards,
Syed Hussain.