Hi,
In my test, the planning calendar (MARC-MRPPP) in combination with lot size PK works in MRP calculation date, but not in ATP.
Example: today is 11/17/11 (Thur), my calendar is configured to have deliveries on weekly Tues, Planned delivery time is 6, GR time is 1. MRP will calculate the following date:
11/17 + 6 = 11/23 (Wed). It would then increase the date to the next Tues (11/29)
11/29 + 1 = 11/30 - this is the result for the requisition date.
If I enter a sales order (ATP check to use RLT) and there is not available inventory, I get confirmed date 11/24! The system takes today 11/17 + 6 + 1 = 11/24. But this is 6 days before MRP can confirm it!
How can I activate ATP to check the planning calendar?
thanks.
Dear Tuffy,
If you set ATP to use RLT then during ATP if stock is not Avail then system goes to MRP 3 view & check the field Tot. repl. lead time. You need to set the no. of days here for RLT. As per my knowledge Planning calendar of MRP2 will not be consider.
Regards
Abhijit Gautam
Thanks Abhijit.
Does anyone know my question.
It would be really good if ATP take into consideration of planning calander, possible?
If possible, how to setup this in the system.
Regards,
tuff