CJ40 cost not been updated in Planned cost report

Former Member
0 Kudos

I am putting cost plan values in Tcode CJ40. But Project Planned cost are been updated in any repory .

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member384980
Participant
0 Kudos

if you are directly doing cost planning in cj40, then use t-code IMCCP3 - Transfer Plan to Project Budget . After then you can view the project Plan reports

former_member388328
Active Contributor
0 Kudos

"Hierarchical Cost planning in CJ40 not updating in CNS41" . Please check this post . It might help you. Next time please do some basic search before positng. If you are still facing the problem , then give the details you have tried.

Thanking you

Vengaiah Chowdary

sunil_yadav2
Active Contributor
0 Kudos

Hi vengaiah chowdary,

I have similar issue, when i am using CJ40 to plan cost at WBS level but the repot CNS41 is not showing this plan cost.

Please suggest

Thanks

Sunil

Former Member
0 Kudos

Have u maintained plan version and currency type?

sunil_yadav2
Active Contributor
0 Kudos

Hello Rakesh,

we are maintaining plan version & currency type.

Plan Cost of CJ40 is correctly shown in CJ41 & CJ30 but not in CNS41.

thanks

Sunil

sunil_yadav2
Active Contributor
0 Kudos

hello all,

Please guide on this.

Thanks

Sunil

former_member388328
Active Contributor
0 Kudos

Hi,

Can please check if your in which month you have planned costs. If it is future month then you cannot see that in cn41, cn41n, cns41.

Thanking

Vengaiah Chowdary

former_member203098
Active Contributor
0 Kudos

select the coloumn Order cost plan 000 from the layout in cns41 and check.if report doesn't display plan value run t-code cjen & cjbn for project.