Escalating actual values to budget

Former Member
0 Kudos

Is there a way to escalate actual values in planning from a previous year by a % into the current year's budget values?

Is loading budget values via catt script the only way you can load them other than manually. Is there a canned sap program you can use that would allow you to load tens of thousands of records?

Thanks,

Jon "Sap Newbie"

Accepted Solutions (0)

Answers (2)

Answers (2)

srinivasa_maruvada
Active Contributor
0 Kudos

For KP26

Enter all related parameters and select F5

Go to MENU-Edit-Change Values

Enter either revaluation factor % or value

You can check for other transactions as well

Srinivas

DaveS4
Contributor
0 Kudos

Hi Jon,

The answer is Yes.

Try KPU1 tcode that creates a "Revaluation

Additional aids are:

-KSPU - Revaluate costs

-KP97- Copy Plan to Plan

-KP98- Copy Actual to Plan

I hope it helps,