on 12-14-2011 5:35 PM
Is there a way to escalate actual values in planning from a previous year by a % into the current year's budget values?
Is loading budget values via catt script the only way you can load them other than manually. Is there a canned sap program you can use that would allow you to load tens of thousands of records?
Thanks,
Jon "Sap Newbie"
For KP26
Enter all related parameters and select F5
Go to MENU-Edit-Change Values
Enter either revaluation factor % or value
You can check for other transactions as well
Srinivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jon,
The answer is Yes.
Try KPU1 tcode that creates a "Revaluation
Additional aids are:
-KSPU - Revaluate costs
-KP97- Copy Plan to Plan
-KP98- Copy Actual to Plan
I hope it helps,
Regards,
Dave
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.