Hello,
I'm both using manual confirmations for production orders and maintenance orders.
For production manual confirmation, it is not possible to confirm operation 0020 before operation 0010. If I'm right, this comes from control key, which has a "milestone confirmation".
For maintenance order, I'm abble to manually confirm in any order, means 0020 before 0010. But I would like to change that and be obliged to follow the steps.
I changed control key, without success. Indeed, I noticed the "(not PS/PM)" mention for "milestone confirmation".
Can you explain me the reason why? Is there any chance to get that result with a different way?
Thanks,
Hello,
Does anybody could confirm if operation sequence with error is not possible in PM/CS order? Otherwise could you tell me how to set up this functionnality (and what I missed, please see answers before)?
Thanks,
Regards,
Olivia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Olivia,
I don't think operation sequence check is available in standard SAP for plant maintenance orders (order type 30)
Please look at the thread below: He got a reply from SAP OSS support team.
http://scn.sap.com/message/8869258#8869258
Also look at this note mentioned below, if you maintain any value other than activity sequence not to be checked, you may even get an error.
Note: 401243
By the way, for sequence checked for operations in PP, you have to maintain in OPK4. Another thing to note is if you have more that one milestone operation for a particular order, you need to confirm the earlier mile stone operation before you can confirm the later one.
For example
0010 : normal operation
0020 : mile stone
0030 : normal operation
0040: mile stone
you cannot confirm 0040 prior to 0020. In other words a miles stone operation cannot confirm previous milestone operation.
Hello,
I had posted this question in PP area. But this is more a PM/CS subject.
Does any PM/CS expert can tell me if operation sequence check is possible or not in PM/CS order?
Thank you in advance.
Olivia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
As mentioned by Anupam, Go to OPK4, select your Plant & Order Type-SM01 and
In Tab-Generally valid settings; goto CHECKS --> Operation Sequence --> Select "Error when operation sequence is not adhered to".
This should work.
Regards,
Anup
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In OPK4 for your maintenance order type and plant combination select under checks> operation sequence>error when operation sequence is not adhered to.
Regards
Anupam Sharma
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.