Hi All,

We are on SAP 8.82 PL01

Currently, we have approval procedures set for A/R Invoice.

We want the same approval procedure to implement for service department.

Our set up is as follows :

Originator

A from Despatch Department

B from Despatch Department

Authorizer

C From Despatch Department

Now we want following addtion

Originator

A1 from Service Department

Authorizer

C1 from Service Department

I tried in the test Db as follows

Added A1 as originator

it updated successfully.

Added A1 as authorizer and system gave me message

can not update existing approval stage. Existing approval processes are based on current stage.

How do i achieve this ?

Or I need to write complete seperate set of queries and create new templates for this ?

Please help.

Thanking you

Malhaar

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

That means the approval procedure is still locked. You need to remove everything that linked to others such as the terms. Uncheck all the documents to try.

former_member218051
Active Contributor
0 Kudos

Hi Gordon,

I tried clearing all the inputs step by step.

but, system did not allow me to do so saying EXISTING PROCEDURES ARE BASED ON APPROVALS.

I ran approval status report for docs not approved and they do exists.

some of them are pending and some of them are rejected.

is this could be the reason why system is not allowing me to add the authorizer ?

if this is the case then how do i add an authorizer ?

or shall i go for altogether new stage ?

in test DB I want to try this by deleting pending drafts ?

how do i do that ?

I'm afraid drafts really get deleted this way ?

thanking you

malhaar

Former Member
0 Kudos

A new stage and procedure would be needed if you cannot eliminate the pending approval.

Former Member
0 Kudos

Actually, you need to clear all. Always is only to clear term. Have you got same error message when you add approver?

former_member218051
Active Contributor
0 Kudos

Hi Gordon,

In first place I made the procedure inactive.

Added the originator

Approval procedure got updated.

Next, I set the term to always and the procedure got updated.

Next, I added the authorizer and system threw the same error message.

Thanking you

Malhaar

Former Member
0 Kudos

Did you update the stage through the link under Stage tab?

former_member218051
Active Contributor
0 Kudos

Hi Gordon,

system did not allow me to update the stage tab.

by updating u mean re selecting ?

b'cos the stage will be the same ?

thanking you

Malhaar

Former Member
0 Kudos

Yes. I mean open the stage by click the arrow under the stage tab.

former_member218051
Active Contributor
0 Kudos

Hi Gordon,

Same error.

thanking you

Malhaar

Former Member
0 Kudos

Hi Malhaar,

I am afraid you have a typo for: Added A1 as authorizer. I believe you mean Added C1 as authorizer.

If that is true, you probably need to uncheck the term for approval first to add new authorizer.

Thanks,

Gordon

former_member218051
Active Contributor
0 Kudos

Hi Gordon,

Yes you are right. It was a typo.

I meant C1 added as authorizer.

Before adding new originator and authorizer i did uncheck active flag for that template.

Thanking you

Malhaaar

Former Member
0 Kudos

The error: can not update existing approval stage means only uncheck active is not good enough. You have to change the term too.

former_member218051
Active Contributor
0 Kudos

Hi Gordon,

I'm confused.

In test DB, there are no pending trasactions.

Still how does it matter to make it inactive and change the term ?

pls. explain

thanking you

malhaar

Former Member
0 Kudos

To change approve procedure stage, the term must be always or none. It is not related to if anything subject to approval or not.

former_member218051
Active Contributor
0 Kudos

Hi Gordon,

As per your instruction I changed term to always.

but same error message.

System is not allowing me to add the authorizer.

thanking you

Malhaar

Former Member
0 Kudos

First you should check is there any document as unapproved with same template ?

if not then you can update it.

One more thing batter make a new template for service document using with query.

Thanks

Manvendra Singh NIranjan

former_member218051
Active Contributor
0 Kudos

Hi Manvendra,

I tried this in test DB. so there are no docs pending for approval.

thanking you

Malhaar