on 04-05-2012 12:05 PM
Hi Experts,
In standard report S_ALR_87013533, when I customize report using Controlling area currency for "Plan" column.
The planned cost of material components display in screen:
But when I customize report using object currency for "Plan" column:
The planned cost of material components disappear in screen.
How can we make the planned cost of material components still appear when changing to object currency?
Please help to advise.
Thanks and best regards,
Khoa Huynh
Is your controlling area currency and company code/object currency same??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please help to advise.
Thanks and best regards,
Khoa Huynh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.