Charm 实施SMDV和SMMN

Former Member
0 Kudos

1,按照标准我们COPY SMDV 到ZMDV。 但是在solar_project_admin创建task list的时候怎么选择用新创建的ZMDV? 在SDN上有的人表示不推荐拷贝SMDV和SMMN。那我们是不是就直接修改SMDV呢。

2, 在CRM WEBUI 中能不能直接创建project cycle和maintenance cycle. 要是可以能告诉我相应的logical links吗? 如果能够创建是不是在这里能够选择SMDV和ZMDV?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member344819
Discoverer
0 Kudos

It is not recommended to use your own transaction type for SMMN/ SMDV.

If you use ZMMN instead of SMMN additional configuration is needed:

1. all the standard CRM configurations (status, actions, etc.) have to

be done for the new type

2. All ChaRM specific CRM configurations (SOCM_MAIN_001) have to be

done for the new type

3. Phase controller settings have to be adjusted for the new type

Kalven