MIGO issuing tolerances

Former Member
0 Kudos

Can I set tolerances during MIGO issuing regarding reservation? Requirement is that issue quantity must be exact or less than defined in reservation.

Is there standard customizing that allows this?

Thank you,

Anna 

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

i hope this in standard that if u issue against reservation, and if u manually increase the quantity in MIGO screen, system will issue a error message.

if this is not the case with u please try making the Message no. M7 362 as error in OMCQ Transaction.

Regards.

Message was edited by: Don ..!!

Answers (4)

Answers (4)

Former Member
0 Kudos

Can I set this tolerance just for particular plan, so it will not influence on other plants?

Regards,

Anna

Former Member
0 Kudos

Nope.. Message setting is not at plant level...

Regards

Former Member
0 Kudos

Thanks a lot Don and Jeevan ! that's the answer that I need

sjeevan
Active Contributor
0 Kudos

Go to OMCQ set message M7 (application area) 362 (message number) to E.

Former Member
0 Kudos

Hi Anna,

yes you can maintian tolerances & limits during GR/IR, you do customizataion in purchasing value keys here you can specify required tolerances by %age wise & assign this purchasing value key in the Material Master Record in purchasing view.

SPRO->MM->purchasing->materail master->define purchasing value keys.....