Display Fields in Object Currency in CN41N.

Former Member
0 Kudos

Hello All,

The requirement is to display some fields  in CN41N Report in Object Currency. Currenlty it is diplayed in CO AREA currency.

SAP has given note no : 1628596 for the same.

However what is confusing in the note is this Quote "After you perform the manual advance steps, implement the correction instructions.". Are we suppose to create the structures as given in the notes or the implementation of the Note will take care of the creation of structures.

This is the note quote.

Reason

In the structure overview, the project structure overview, the progress analysis, or the project planning board, you cannot display costs and finance data in the object currency.
This note delivers the implementations to use the function.

Other terms

Customer connection, Product Lifecycle Management, Project System
Object currency, CN41, CNS41, CN41N, CNE5, CNSE5, CJ2B, CJ2C, interface note, CustConn

Reason and Prerequisites

A function is missing.
You must have implemented Notes 1626081, 1628475, and 1628595.

Solution

Improvement

You can also display accounting data in the object currency on the project planning board, as well as in the structure reports.

Customer uses

One report is now sufficient to analyze accounting data in the controlling area and the object currency in parallel.

Delivery

After you perform the manual advance steps, implement the correction instructions.

We recommend that you import the relevant Support Package because using transaction SNOTE to implement the note requires many manual steps.
Due to the complexity of the changes (creation of structures, of the BAdI, etc), they should only be implemented by experienced developers.

5 REPLIES 5

Former Member
0 Kudos

Do the manual steps involve creating the structure?

Rob

0 Kudos

Yes.there are stucutes..data elements and in the end a BADI too. SAP has given a long list of things to do..I have pasted this below..

------------------------------------------------------------------------
|Manual Pre-Implement.                                                 |
------------------------------------------------------------------------
|VALID FOR                                                             |
|Software Component   SAP_APPL                      SAP Application   |
| Release 470          Until SAPKH47036                                |
| Release 500          Until SAPKH50025                                |
| Release 600          Until SAPKH60020                                |
| Release 602          Until SAPKH60210                                |
| Release 603          Until SAPKH60309                                |
| Release 604          Until SAPKH60410                                |
| Release 605          Until SAPKH60506                                |
| Release 606          Until SAPKH60601                                |
------------------------------------------------------------------------

    1. In the ABAP Dictionary (transaction SE11), create the following data types with reference to the domain WERTV8 (package KAHF):

              (The components are specified in uppercase followed by the short description. Before you perform point 2, save, check, and activate these.)

           AUFERLPLANOC (Current Order Revenue Plan In Object Currency)

           AUFERLPLN2OC (Order Revenue Plan (Version 2) In Object Currency).

           AUFKSTPLANOC (Current Order Cost Plan In Object Currency)

           AUFKSTPLN2OC (Order Cost Plan (Version 2) In Object Currency)

           AUFTRANFOC (Residual Order Plan In Object Currency)

           BUDGETOC (Budget Of A Task (Request Variant Replaces OC))

           DEBFINPLNOC (Current Customer Financial Budget In Object Currency)

           DZHLNGOC (Customer Total Payments (Down Payments And Payments) OC)

           FESTPROBLOC (Fixed Price Commitment In Object Currency)

           FREIGABEOC (Release In Object Currency)

           ISTERLOESEOC (Actual Revenues In Object Currency)

           ISTKOSTENOC (Actual Costs In Object Currency)

           KREDFINPLNOC (Current Vendor Financial Budget In Object Currency)

           KSTOBLGESOC (Total Cost Commitment In Object Currency)

           KZHLNGOC (Vendor Total Payments (Down Payments And Payments) OC)

           PROERLPLANOC (Current Project Revenue Plan In Object Currency)

           PROERLPLN2OC (Project Revenue Plan (Version 2) In Object Currency)

           PROKSTPLANOC (Current Project Cost Plan In Object Currency)

           PROKSTPLN2OC (Project Cost Plan (Version 2) In Object Currency)

    2. In the structures RPSCO_LIS, CNZVR, and STRUCR_BEFORE_RPSCO, create the field OWAERS with the component type OWAERS after the field WAERS.

              (Here and in the following sections, the components are specified in uppercase followed by the component type. Before you perform the next numbered point, save, check, and activate these.)

    3. Create the structure RCJ_RPSCO_LIS_OC with the short description "RPSCO_LIS for graphic (object currency)" in the package CN_PPT_GRAFIK. The fields that you must insert are:

           Component       Component type

           PROKSTPLAN_OC  PROKSTPLANOC

           PROKSTPLN2_OC  PROKSTPLN2OC

           AUFKSTPLAN_OC  AUFKSTPLANOC

           AUFKSTPLN2_OC  AUFKSTPLN2OC

           PROERLPLAN_OC  PROERLPLANOC

           PROERLPLN2_OC  PROERLPLN2OC

           AUFERLPLAN_OC  AUFERLPLANOC

           AUFERLPLN2_OC  AUFERLPLN2OC

           KREDFINPLN_OC  KREDFINPLNOC

           DEBFINPLN_OC   DEBFINPLNOC

           BUDGET_OC      BUDGETOC

           FREIGABE_OC    FREIGABEOC

           AUFTRANF_OC    AUFTRANFOC

           FESTPROBL_OC   FESTPROBLOC

           KSTOBLGES_OC   KSTOBLGESOC

           ISTKOSTEN_OC   ISTKOSTENOC

           ISTERLOESE_OC  ISTERLOESEOC

           KZHLNG_OC      KZHLNGOC

           DZHLNG_OC      DZHLNGOC

              On the "Currency/quantity fields" tab, enter the reference table RPSCO_LIS and the reference field OWAERS for all fields.

    4. Create the structure RCJ_EVVALUE_OC with the short description "Progress analysis: Progress values (PV; object currency)" in the package CN. The fields that you must insert are:

           Component       Component type

           EV_PLAN_ORG1_OC  EVPLANORG1

           EV_ACT_ORG1_OC   EVACTORG1

           EV_ACT_CORR1_OC  EVACTCORR1

           On the "Currency/quantity fields" tab, enter the reference table RPSCO_LIS and the reference field OWAERS for all fields.

    5. Create the structure RCJ_EV_OC with the short description "Progress determination (object currency)" in the package CN. The fields that you must insert are:

           Component       Component type

           .INCLUDE                RCJ_EVVALUE_OC

           EV_COST_VAR_ORG_OC      EWALVARORG

           EV_SCHED_VAR_ORG_OC     EVSCHVARORG

           EV_SCHED_VAR_CORR_OC    EWALVARCORR

           EV_COST_VAR_CORR_OC     EVSCHVARCORR

           On the "Currency/quantity fields" tab, enter the reference table RPSCO_LIS and the reference field OWAERS for all fields.

    6. Create the structure RPSCO_LISC_OC with the short description "RPSCO_LISC object currency" in the package KAP0. The fields that you must insert are the two structures that you created above:

           Component       Component type

           .INCLUDE     RCJ_RPSCO_LIS_OC

           .INCLUDE     RCJ_EV_OC

    7. For the structure RCJ_RPSCO_LIS, create the append structure RCJ_RPSCO_LIS_APPEND with the short description "Append structure RCJ_RPSCO_LIS" in the development class KAP0.. Add the following entry:

           Component       Component type

           .INCLUDE     RCJ_RPSCO_LIS_OC

    8. For the structure RCJ_EV, create the append structure RCJ_EV_APPEND with the short description "Append structure: Progress determination" in the development class CNEV. Add the following entry:

           Component       Component type

           .INCLUDE     RCJ_EV_OC

    9. Start the report RCNCT001 (in transaction SE38) in order to generate the includes for the PS information system again: Choose "PS Info System Structures" and then

           select "Structure Overview" (Field string name STRUCR, Include name RCNSTRUCR)

              Execute the program; the system should highlight the new fields in color. Add the new fields to the following groups ("Grp" column):

           PROKSTPLAN_OC             COST

           PROKSTPLN2_OC             COST

           AUFKSTPLAN_OC             COST

           AUFKSTPLN2_OC             COST

           PROERLPLAN_OC             REV

           PROERLPLN2_OC             REV

           AUFERLPLAN_OC             REV

           AUFERLPLN2_OC             REV

           KREDFINPLN_OC             FIN

           DEBFINPLN_OC              FIN

           FESTPROBL_OC              OBLG

           KSTOBLGES_OC              OBLG

           ISTKOSTEN_OC              COST

           ISTERLOESE_OC             REV

           KZHLNG_OC                 FIN

           DZHLNG_OC                 FIN

           EV_PLAN_ORG1_OC           EVVL

           EV_ACT_ORG1_OC            EVVL

           EV_ACT_CORR1_OC           EVVL

              Start the generation of the includes (Shift + F4).

    10. Start the report RCNCT001 again and perform the same steps as described above for:

           "Period Drilldown" (Field string name CNZVR, Include name RCNCNZVR).

             

    11. In the program SAPLCNIS, create the following text symbols (choose "Goto -> Text Elements -> Text Symbols):

           Name         Text

           ACL        Order Revenue Plan OC 000

           ACM        OrdRevPlanOC000

           ACR        Order Revenue Plan OC 000

           ACS        OrRevPlOC000

           AOL        Order Cost Plan OC 000

           AOM        OrdCostPlanOC000

           AOR        Order Cost Plan OC 000

           AOS        OrCstPlOC000

           PCL        Project Revenue Plan OC 000

           PCM        ProjRevPlan OC 000

           PCR        Project Revenue Plan OC 000

           PCS        PrRevPlOC000

           POL        Project Cost Plan OC 000

           POM        ProjCostPlan OC 000

           POR        Project Cost Plan OC 000

           POZ        PrCstPlOC000

    12. Create the following text symbol in the programs SAPLCNFS and RCNFS000:

           Sym          Text

           POC        Costs (OC)

          

To ensure that the fields for the object currency are visible, you must set the field OBJ_CUR_FLG of the structure SWITCH_VALUES to 'X' in the implementation of the BAdI PS_FUNCTION_SWITCH (enhancement spot ES_PS_BADI).

0 Kudos

then you have to do them.

It sounds like importing the support package would be the better option.

Rob

0 Kudos

Well Rob,

Currently we are on support pack 19..and the required functionality is in support pack 21.

So you mean If I ask the basis team to import the pack 21..all of this creations of different objects will be taken care of..

Thank you for the inputs,

Rajesh.

0 Kudos

I think so; however, you could raise an OSS message to confirm this.

Importing support packs isn't a risk free strategy either. You will have to run transaction SPAU after the support pack is implemented to see if you have further work to do. And you will have to test.

Rob