commited qty is 0 at ATP check

Former Member
0 Kudos

Dears,

Could You, pls help me with ATP-check settings - planned orders for REM

I have 4 plants in one company / more plant in a client. I set avaialbiltiy check at plant level OPPQ, OPPR, also maintained the role / scope etc. materials are ok with avail. check code - and still: for one plant, the check is done correctly, for others the check runs, but always give result as commited qty 0.

Same rule PP, same avail code Y2, same scope, same settings in OPPQ - and still different result.

Could any of You pls tell me, what do i miss here?

Please no basic answers!

Thanks in advance

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Check the strategy group..

if it is 40 (Planning with final assembly) , no issues...

Check and revert back...

Regards,

PSM

Former Member
0 Kudos

Hi there,

thank You for answering - but NO strategy group is used in any plant: material masters are identical in Plant A and Plant B in my test scenario.

(In strategy only the option of running or not running the availability check is defined - and my ATP check itself is done, MDVP shows this, but committed qty is 0 / false).

Br

Former Member
0 Kudos

Hi,

Do maintain the strategy group 40 then check...

Check and revert back...

Regards,

PSM

Former Member
0 Kudos

Hi There

I colse this thread - solved on my own.

FYI - despite my previous informations, OPPR and OPPQ has nothing to do with this action - check rule is not set to be there.

former_member186193
Active Contributor
0 Kudos

Hi,

What is the strategy group of the material for which you are checking ATP?

Regards,

Alok Tiwari

Former Member
0 Kudos

Hi There,

thank You for answering

it is Y2 (as I have mentioned), identical copy of 02.

Also: we are talking about REM planned order ATP-check

Br