Dear experts,

                            During planned order to production order conversion from APO,system throws error message "Only two decimal places are permitted for unit of measure M"& queue blocked eventually no planned order conversion to production order

We have maintained two decimal places for unit of measure M in ECC & APO as well.

Appreciate your inputs!

Regards

Milind

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello,

Please refer SAP Note 362932 - Conversion with proportion/product units.

Please consider the two fields for the decimal places: For example the display decimal place is taken into account in the list output; onto the rounding decimal place, for example, it is rounded during the creation of a production order. The rounding decimal place is not, however, considered by every transaction so that particularly in the case of a simultaneous use of metric and non-metric units it is recommended to set the rounding decimal places of these units of measurement to 3 (like the number of the decimal places of the quantity fields). Additional information is available in Note 77525

Hope this helps