on 07-16-2012 1:54 PM
Hello
We have recently upgraded to BI 4.0 SP 4.
When I try to schedule a index to run every day I get the following error:
"Failed to update the information space
for input string: "NaN"
If I try schedule on hour or weekly I still get the same error message.
Is this a known bug in SP4 because scheduling of indexes worked perfectly on BI 4.0 SP2 patch 12?
Regards
Graham
I can't say that I've seen this error in past versions or in SP4. And it doesn't look to be referenced in the errors guide either. But these are things to consider...