Deliverydate in the delivery

Former Member
0 Kudos

Its a STO process, delivery is created with reference to a PO.

Delivery date in the PO and the date in the reference delivery are different.

In the PO -  Planned delivery time(From Material master) is used to determine the delivery date which is correct and it is in the delivery schedule tab as well.

In delivery i guess its scheduling again taking delivery creation date as picking date + transportation lead time = delivery date in the delivery document.

What configuration changes are needed to have the same delivery date as in PO?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member182609
Active Contributor
0 Kudos

Check the configuration in SPRO

SPRO-->Logistics Execution-->Shipping-->Basic Shipping Functions-->Scheduling-->Delivery Scheduling and Transportation Scheduling

Check settings in your system.

Former Member
0 Kudos

Sridhar,

Thank you for the reply.

In the above mentioned setting we can only set scheduling by shipping point in my case ( as delivery is created from a PO)

former_member182609
Active Contributor
0 Kudos

Is it inbound delivery are you taking about ? then check the how inbound delivery created.If it is vendor ASN then vendor might have provided the delivery date.

Refer some info on this.

http://help.sap.com/saphelp_46b/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/content.htm