on 07-25-2012 4:16 PM
Its a STO process, delivery is created with reference to a PO.
Delivery date in the PO and the date in the reference delivery are different.
In the PO - Planned delivery time(From Material master) is used to determine the delivery date which is correct and it is in the delivery schedule tab as well.
In delivery i guess its scheduling again taking delivery creation date as picking date + transportation lead time = delivery date in the delivery document.
What configuration changes are needed to have the same delivery date as in PO?
Check the configuration in SPRO
SPRO-->Logistics Execution-->Shipping-->Basic Shipping Functions-->Scheduling-->Delivery Scheduling and Transportation Scheduling
Check settings in your system.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is it inbound delivery are you taking about ? then check the how inbound delivery created.If it is vendor ASN then vendor might have provided the delivery date.
Refer some info on this.
http://help.sap.com/saphelp_46b/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/content.htm