on 08-03-2012 11:21 PM
Hello All,
I would like to use SAP to record the results of weekly tests that are performed on parameters, like temperature, humidity and microbial count of the air (essentialy.... productions conditions).
My questions is what is the best way to summarise this data:
As an example, I have tried to do the following:
1. MM01: Chemical Industry, PRT
2. Selected: Basic Data, QM and PRT Views,
2. QM Setup : Defined Insp Type 14.
2
The error says " You cannot assign inspection type 14 to a material"
I also tried to create a PRT with CF01, but I can not get beyond that point. How do I create an inspection plan for this PRT and associate it to it ?
Any ideas ?
Kind Regards
S Gupta
hi
Inspection Type 14 Belongs To Calibration Lot,
Inspection Type 14 is assigned Only For Equipments,You cannot able to assign it for materials.
Create PRT-1 as Equipment in IE01
Create Task list in IA01 and assign the frequency such as 1W,6m etc.
Assign task list to Maintenance Plan (IP42) and Schedule it in IP30 , So Maintenance Order Will Assigned To 14XXXXXXXXXX lot,So for This Lot You Can able to RR,DR, and UD Is Possible,Consecutive Lots Will Automatically generated, Based on Bgnd Scheduling
Regards,
U.Linganathan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
14X triggered successfuly...many thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for all your responses, yes these are all very nice suggestions. Still I have a few doubts:
1. I was not able to check if inspection Type 14 is active in SPRO IMG, do you know where its defined ?
I think you may right Type 14 is not defined here (look at the screen shot usage does not list 14)
2. PM Counter sounds like a good idea. It is industry standard to use this kind of inspection for monitoring parameters ? Are there any other strategies ?
All will get points...
Kind Regards
SG
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
My dear frnd
why u r using this against this requirement, u need to record the results against some parameters, its better to use PM-counter here, create Characterstics and record daily weekly results against the parameters. There are stdn reports are also available.
Why u need to create a plan, scheduling and all type of time consuming processes, once create the characterstics then record daily as per the counter execution.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Linganathan,
Thanks for your kind suggestions. I followed all the steps as you suggest. However I had trouble as the system kept asking for maintainence package. Some how I could fix that also. However still the system is not generating any inspection lots for this perticular instrument at regular intervals ( I gave daily). I searched for insp lots for the instrument in QE51N, nothing !
Any idea what I may be doing wrong ?
SG
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.