How delivery time ( EBAN-UZEIT) will come while creation of PR

Former Member
0 Kudos

Hi Guys,

could you please tell me How delivery time ( EBAN-UZEIT) will come while creation of PR.

my requirement is need to populate delivery time in third party PR.

Appreciate your help.

Kuber

Accepted Solutions (0)

Answers (3)

Answers (3)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

Check and Set,Planned Delivery Time in MRP -2 view of material master where it determine!


OR

Check and Set to use BADI or User Exit to serve your purpose of trggering Delivery Time.

Regards,

Biju K

bsivasankarreddy_reddy
Active Contributor
0 Kudos

hi

PR for third party process

when you create the third party order on that time system create automatic PR, here all relevant data copy sale order to PR.

as for you question  EBAN-UZEIT  , this is copy for sale order schedule lines , delivery date and time

this is comes VBEP-EZEIT, based on this system will copy the EBAN-UZEIT

its totally depending on sale order schedule line  , VBEP table

Former Member
0 Kudos

Hi Siva,

Thanks for your answer, I have tried to add manually VBEP - EZEIT and created sales order.

But it does n't copy to EBAN-UZEIT. Any idea to get this.

we are into ECC6 EHP 5

Regards,

Kubera

Former Member
0 Kudos

Hi All,

could you please advice on my query.

Regards,

Kuber

JL23
Active Contributor
0 Kudos

can you explain this part in more detail:  I have tried to add manually VBEP - EZEIT and created sales order.

have you jsut tried or have you succesfully done?

where did you do that, transaction please.

Former Member
0 Kudos

Hi Jurgen,

I have added VBEP - EZEIT time thru VA01 transaction created third party sales order successfully.

But this time not copied to EBAN-UZEIT.

how it get update from sales order.

Regards,

Kuber

Former Member
0 Kudos

Hello Kuber,

The requirement is quite interesting and valid.

I tried it via purch req delivery scheduling BUT SAP standard does not allow such for third party order processing.

Former Member
0 Kudos

Hi Kuber,

1. Manually created PR (without any source assigned):

The system will suggest the Today's date as the Delivery Date but will display a warning message

But remember upon carrying out source determination the system will suggest a message about the Delivery Date "Can delivery date be met? (Realistic delivery date: &&&&)" from the Purchasing Info Record.

2. Auto generated PR through Sales Order/ MRP Run (with source assigned):

The system will create the PR with Delivery Date details using the following details:

Planned Delivery Time (can be maintained in MMR - MRP 2 View or in Purchasing Info Record for the Vendor Combination in ME11)

GR Processing Time (can be maintianed in MMR - Purchasing View or in MRP 2 View)

/Manoj