on 10-01-2012 11:03 AM
Hi Friends,
There are 2 IDOCs MATMAS and CLFMAS processed sequentially and received through PI. I can see the both the IDOC status with 75. I need both the IDOC should be with status 64 to process further.
We have implemented serilization concept to process both IDOC sequentiually.
I find a report RSEINBQUEUE which can be used to process IDOCS are there in the queue WEINBQUEUE.
Is it the right approach to process IDOCS are in 75 status and move to 64?
Please confirm me whether I am following correct approach. else let me know the solution with steps.
Any help highly appreciated.
Thanks
Santosh
moved from SAP ERP - Logistics Materials Management (SAP MM) to ABAP Connectivity
Please check OSS Note 817939 - IDoc: IDocs remain in status 75
It explains why it can happen, what you can do and has even a program code correction
Message was edited by: Jürgen L
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm not sure if this is the correct way, but you can use report RC1_IDOC_SET_STATUS in SE38 to change the status of the IDOC's.
/Manoj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.