Hi Gurus,
Our client has got stock transfer orders between their plants.
I have observed that when an STO is created, the dates are calculated as below
1. In ECC - based on planned delivery time in material master or purchasing info record
2. In APO - using transportation lane time
If user changes the planned delivery time in STO in ECC, the dates are recalculated (for example reducing planned delivery time to 10 days from 20 days). But this rescheduling changes are not passed to APO. APO still has the old dates based on the transportaion lanes.
/N/SAPAPO/CP3 settings says Always Retransfer. Curious to know whether there is something missing to make both systems in sync.
I dont get the date difference in delta report as well.
Thanks,
Gijoy
I have similar issue where in user is changing the PDT of STO in ECC and expecting the delivery creation dates to be reflecting in APO.
Publication setting is maintained with Always retransfer in APO, i have also tried suppress the rescheduling of the stock transport order setting in ECC.I have checked in the indicator.but it seems to be not working.
Could you please let me know if there are any other settings to achieve the requirement
Regards,
Meghana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can change suppress the rescheduling of the stock transport order in APO by using the following SPRO setting in ECC
Integration with Other SAP Components->Application Specific Setting and Enhancements->Setting and enhancements for external procurement->outbound processing of purchasing data->Suppress Rescheduling of Stock Transport Orders in Target System
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The setting to suppress the rescheduling of the stock transport order in APO if it has been changed in ECC. If you have this on then APO will not change the start date of the stock transport order based on the transportation lane duration.
For example if you have changed the PDT in the STO in ECC, you might not want it to reschedule it in APO based on the transportation duration on the lane.
This is only available in ECC 6.0 and not in R/3 4.6
Hii Joe,
Please check the calendar assignment in ECC and APO( timestream), whther they are same or not ? and go through the following link....
http://scn.sap.com/message/13657395#13657395
Regards
Debashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Debashis,
The issue is not when system scheduling the orders. It is when we manually change the date in PO in R/3. Say we reduce the planned delivery time in the PO, the delivery date changes or if we change the route, the delivery date changes. Or even they can change the date manually in R/3. These changes are not reflected to APO.
Thanks,
Gijoy
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.