How to unrelease Production order

mohan_kishore
Explorer
0 Kudos

Dear All,

Pl tell me how to unrelease the released production order

Regards

MK

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Mohan,

If you want to revoke the status from REL to CRTD, then follow the menu path ( Functions -> Read PP master data). This can be done if you have not done your GI and confirmations.

While Reading the master data, system once agains select the BOM and routing and explodes the both. Material availability, scheduling and costing will be performed once again.

Former Member
0 Kudos

Hi Mohan,

Once you release the production order the status will be changed to REL.By un releasing do you mean that again the status should be CRTD.Go to change status ( cor2 icon <i> then go to status  tab & go to status witiout status box untick the NOPV(Production ver. change not aollowed) now then you have to postread master data(From Menu prod. ord--> Functions-->postread PP Master Data nor (Ctrl+shift+F1)).Once you do this the status of the production order will be changed from REL to CRTD. now order flag is active

Regards

Vn

Former Member
0 Kudos

Hi,

Once you release the production order the status will be changed to REL.By un releasing do you mean that again the status should be CRTD.If yes then you have to read master data(From Menu Functions-->Read PP Master Data).Once you do this the status of the production order will be changed from REL to CRTD.In order to carry out this step goods issue,confirmations should not happen.

CSN