on 05-16-2013 11:12 AM
Hi,
Here there is a scenario for my client as follows.
We are doing maintenance activity in a plant, and there is a necessity of capacity planning.
In work center the start time and end time are mentioned as 09:00:00 and 17:00:00 (total 8 hrs er day).
After that we are using this work center in PM order in for an operation duration 10 hrs.
So while scheduling, if capacity is over loads, the distribution is taking place as 5 hrs for the first day and the remaining 5 hrs for the next day.
Ideally it should be 8 hours in first day and 2 hours in next day.
I have mentioned distribution key as SAP000 in WC capacity screen. But no change of distribution.
I dont know where and what I missed.
Please guide me to get the capacity distribution with 100% utilization of capacity.
Regards,
Check the capacity load of that work center in CM01 / CM02 / CM03. Some other might have occupied the first 3 hours of that work center load.
What is the start time in this order for that operation??
Is there only one operation with that work center in that order or you have some other operations as well with same work center??
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The capacity of the WC is not utilized by some other order.
The start time of the operation is 09:00:00, which is same as my WC start time.
If it is only one operation, the distribution is fine. But I am facing problem while maintaining 2
operations in the same PM order.
After scheduling, when I releasing the order, it is saying, capacity overload. If I chose for Detailed Info, it is showing as shown in the image.
Here
In Operation 0010 - 12 hrs
In Operation 0020 - 12 hrs
WC availability per day is 8 hrs.
So distribution should be
8 hrs for 17.05.2013 - Which is 100%
8 hrs for 18.05.2013 - Which is 100%
8 hrs for 20.05.2013 - Which is 100%
Over load - Nil
But it distributed as
6 hrs for 17.05.2013 - Which is 75%
12 hrs for 18.05.2013 - Which is 150%
6 hrs for 20.05.2013 - Which is 75%
Over Load - yes.
Please tell me where i am missing the settings. Solution will be highly appreciated.
Regards,
Hi Vinodh,
Can you check whether you have flagged the "Relevant for finite scheduling" field under Capacity tab of Workcenter ?
Also, ensure that in OIOI, for "Capacity availability", "No check" box is unflagged (not selected).
Regards,
Balachandar L
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In work center Relevant for finite scheduling is enabled. And in OIOI, Capacity Availability - No Check is not flagged. And also Capacity Profile also maintained.
Here the problem is while distributing the capacity of the work center, the total capacity is not utilizing 100%.
Example:
The work duration is 12 hrs in operation. Available capacity of the WC is 8 hrs per day.
Now the distribution is happening as 6 hrs for first day and remaining 6 hrs for the second day.
But how we need the distribution is 8 hrs in first day (To utilize the WC capacity 100% in first day) and remaining 4 hrs in second day.
Hope I have clarified you regarding my issue.
Regards,