Program to close internal order

jyoti_singh3
Participant
0 Kudos

Hello All,

I am using the t-code KOK2 to create the variant for the program and was trying to use the t-code KOK4 to close the IO selected based on the variant created. Here i can see an option to put the IO status to complete but there is no option for putting the  status to closed.

If anyone used any standard method for changing the IO status to closed,please share it with me. We are just using three status for IO, Released, Teco and closed.

Best Regards

Jyoti

Accepted Solutions (0)

Answers (1)

Answers (1)

sanilbhandari
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi

You have to use the report RKOSEL00 to close the IO collectively. Note that you have to first TECO the IO before you can close them.

Thanks & Regards


Sanil Bhandari