Change in Date of Manufacture even the Process order is TECO & changed to REL

vinay_pasalkar
Participant
0 Kudos

Hi Experts,

Could you please let me know if it is standard process that once the PO revoked from Technical completion, the date of manufacture & Basic End & start date is changed.

Or Ideally once the order is TECO then there should not be any further changes in process order.

Thanks

Vinay

Accepted Solutions (1)

Accepted Solutions (1)

dejoy
Active Contributor
0 Kudos

Hello Vinay,

Why would you it after teco,Ideally it should not be changed after TECO and also it will not change dates in process order.

Regards,

vinay_pasalkar
Participant
0 Kudos

Thanks Dee. Just wanted to confirm how it should work ideally.

dejoy
Active Contributor
0 Kudos

Hello Vinay,

see you need to revoke status teco  sometimes as

1.if your order is not complted but to perform month-end activities.

2.If you need to alter any data in the orde.

After teco order

1.reservations and capacity requirements are deleted.

2.Not MRP relevant.

Regards,