on 08-13-2013 10:27 PM
We have a scenario where Demand Flows from one Plant to another from Service Order.
Suppose Plant A to Plant B.
In Both the Plants we have used MTS strategy, the only difference is MRP4 Ind Coll Req
The Demand is Generated from Plant A and is transfered to Plant B.
We have MRP 4 Ind Coll Req as 2 in Plant A
And MRP 4 Ind Coll Req as 1 in PLant B
So when We Create Service Order for Material in Plant A then System doesn't allow to create PR for Sub Contratcing ( SPecial Procurement Key is set).
Is there any way to control Ind Coll Requirement according to Order Type.
Thanks in Advance for Help
Hello Gaurav,
Dont think it is possble..
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gaurav
As far as I know, the setting is only available at material level, nor for the order type.
BR
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.