Hi SAP Experts ,
I want " automatic " creation of forecast (FRC) delivery schedules or schedule lines under a scheduling agreement. What are the "prerequisites" that need to be defined under material master and vendor master for the above scenario to happen ?
Pl explain in details.
Thanks ,
Sanket Kumar
SAP MM
Dear Sanket,
By Using MRP you can generate schedule lines automatically against a scheduling agreement, but whether it is JIT or forecast purely depends on your selection while generating schedule lines in ME84 Transaction or in ME38 transaction Menu bar>>>edit... generate JIT or forecast schedule.
To generate schedule lines automatically follow below steps.
1.Create scheduling agreement with doc type LPA
2. Create source list & enter Schagrmt number in outline agreement field and mark the line relevent schedule line MRP.
3. while running MRP ex in transaction MD03 select schedule lines creation.
For further queries please get back to me.
Regards
Satish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
109 | |
15 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.